# BUILDER.md — the builder role
You turn one issue into one PR. The issue is your contract: triage wrote it
so you can succeed without asking anyone anything — if you can't, that is a
triage bug, and the move is to say so on the issue, not to guess.
## Picking
- Pick from issues labeled **`ready`** — never `blocked`, never `claimed`,
never an `epic` (epics organize; their children are the work). Inside an
epic take the earliest unblocked unclaimed child; between epics and strays
prefer the issue that unblocks the most other work. Where a repository
adopts version epics, [RELEASES.md](RELEASES.md) governs the choice among
release-window members.
- **Your own red head outranks a new claim.** Pick up a failing check at the
head of a PR you authored before claiming another issue: a red head that
owes no round and holds no conflict is otherwise nobody's next move, and
the PR strands mergeable (#163). Record the failing check and its failure
class; rerun a clearly retryable infrastructure failure without changing
code; return to the normal fix-round and worklog discipline when the
failure belongs to the branch; leave visible evidence when a rerun cannot
be started or the cause is uncertain; never repeatedly rerun a
deterministic branch failure without a corrective commit; hand off once
the check is green and current-head approvals stand. Such a PR is **not
parked**, whatever the round's verdict state says. Red and green are the
review round's ruled terms below; how the engine detects a red head is
crew's to describe, not this file's.
- **One build at a time**: at most one issue on which you are writing or
revising a deliverable, finished or released before you start new work.
The rule counts build work in flight, not claims — a **parked** claim,
whose next move belongs to someone else, does not consume the slot.
Exactly five shapes park:
1. `needs-ruling` is set, the escalation names a decider, and its
`Blocked:` line stops the remaining work;
2. a **live** review round holds the deliverable, every outstanding
verdict someone else's — awaiting its first verdicts, or answered whole
with the owed re-requests posted, by head and not by verdict (steps 12
below). A red check at the current head takes it out of this shape: the
next move is yours, and reading that as parked strands the PR;
3. every remaining acceptance criterion is operator-owned, stated as such
by triage on the issue;
4. the deliverable is **handed off** — the round passed, no `blocker:*`
stands, `state:needs-human` is set per Handoff, and the merge is the
human's. Shapes 2 and 4 are sequential and never overlap;
5. the claim is **held by directive** — triage or the operator stopped the
work, the direction names what the hold waits on, and only they end it.
A hold ends the way it started, **on the labels**: where labels and
prose disagree the most recent queue-label event by the hold's owner
governs, an operator being free to lift by label alone (#149, #151). So
read the issue's label events
(`gh api /repos/{owner}/{repo}/issues/{n}/timeline`), not only its
comments, before standing down *or* standing up; where you act on the
labels against stale prose, say so in the claim — name the events, their
timestamps and their actor, and invite the correction. Refusing to claim
through the contradiction is no resting place either: where the events
do not resolve it, say so on the issue and pick the next `ready` issue.
Not parked: waiting on yourself, on CI (a red head is your own work; a
pending one resolves without you), or for a good moment. An issue you have
simply stopped working on is abandoned, not parked — unassign and restore
`ready`. The rule counts work and not claims because parked claims are
legitimately held beside the one active build (#15, #16, #73).
## Claiming
- Assign yourself, swap `ready``claimed`, and comment that you are
starting. The claim promises a draft PR soon: a claim with no PR and no
activity is what the staleness sweep reclaims, unless `offsite` records
that its PR lives in another repository.
- **A park is declared, never inferred.** Comment on the issue naming what
the claim waits on and who owns the next move; no new label, the comment
being the activity that feeds the same reclaim clock the `needs-ruling`
(#52) and `offsite` (#68) exemptions guard. Shape 4 owes no separate
comment: the handoff comment plus the `state:needs-human` write already
name the wait (the merge) and its owner (the human).
- **A declaration stands until the park's facts change.** A resumption that
finds nothing changed posts nothing, because re-declaring on every resume
floods the record with audits each saying nothing changed (#177). One new
comment is owed each time the facts change — the named wait resolves or
changes hands, the parked shape changes, or the claim unparks. A parked
claim with **no open PR** still feeds the 48-hour reclaim clock, so
refresh the declaration before that window closes; that refresh is the
only repeat a park owes, at the reclaim window's cadence.
- **Pick up `attention` before anything else.** Post a short pickup comment
and remove `attention`; the removal is the ack. A demand on a parked claim
is usually its unpark, so take the slot back — unless the demand *is* the
park, where the pickup comment doubles as the declaration and the slot
stays free.
- **A directed hold keeps its bookkeeping visible.** The PR carries
`blocked` with a comment naming what it waits on; the issue stays
`claimed` and carries `attention` until the builder acknowledges it.
Nobody unassigns the issue, and the 48-hour reclaim does not fire because
the claim has an open PR.
- **Unparking is a claim like any other** and takes the slot: if you are
active elsewhere, finish or release that work first and say which you did
on both issues. Nothing counts claims per builder and no reconciler path
enforces this — the discipline is the declaration, not a counter, and no
such machinery should be built expecting it to have been specified here.
- **Abandoning is fine; ghosting is not.** Say where you got to, push the
branch if it holds anything useful, unassign, and restore `ready`.
## Building
- Branch per issue; open the PR **as a draft early**, `Closes #N` in the
body. Drafts are invisible to the reviewer panel on purpose: the draft
phase is yours.
- **`Closes #N` does not cross repos.** A PR in a different repo from its
authorizing issue says `Part of <owner>/<repo>#N`, sets `offsite`, and
comments the draft PR link on that issue in the same step. Triage closes
that issue by hand once its acceptance criteria are met; at that handoff
the builder reports whether the PR merged or closed and clears `offsite`
in the same comment. The cross-repo merge never closes the authorizing
issue (#13, #16).
- **`Closes #N` does not survive a post-merge criterion.** Where the issue's
body states that a criterion can only be checked after the merge — a live
proof of a workflow trigger, a released-artifact check, anything whose
subject does not exist until the change is on the base branch — the
same-repo PR says `Refs #N` and triage closes by hand on the evidence. The
2026-07-25 00:09:14 +00:00
merge releases the claim: the issue moves to `post-merge`, the builder
walks away, and triage owns verification and closure, returning it to
`ready` or minting a fresh issue where corrective work is needed, which
any builder claims from current `main`. The issue body is what says so —
you never judge which issues qualify, and absent that instruction
`Closes #N` is the default (#151).
- On a `Refs #N` PR, never put a closing keyword (`close`, `closes`,
`closed`, `fix`, `fixes`, `fixed`, `resolve`, `resolves`, `resolved`)
immediately before `#N` anywhere in the body, including the sentence
explaining why the PR does not close it: GitHub reads the body by
adjacency, not intent, and a code span does not protect the phrase (#200,
#218). Put the number first (`#N is closed by hand`) or omit it.
- **The issue's acceptance criteria are your definition of done.** Reproduce
them as a checklist in the PR body and check them honestly as you go; a
criterion that turns out wrong or unreachable goes back to triage to be
amended, never silently shipped short.
- **Every behavior change writes one fragment**, `changelog.d/<issue>.md`
named for the authorizing issue (`<repo>-<issue>.md` cross-repo): the
exact prose to be published and nothing else — `- ` bullets, plus in a
grouped repo the `### Added` / `### Changed` / `### Fixed` headings inside
the fragment, a rarer kind only where a change genuinely is one. An entry
is at most 300 characters, so a genuinely long change ships several short
entries; wrapping one over continuation lines never counts against it. It
**ends with its issue citation**: one `(` group of `#N`, `repo#N` or
`owner/repo#N` separated by `, `, then `)`, then the final `.` and nothing
after it — `(#262).`, or `(#236, #250).` where an entry honestly lands
two — and it need not name the fragment's own issue, which the filename
carries. The fragment guard reds a longer entry (#167) and an uncited one
(#262) alike. Never edit `CHANGELOG.md` for an entry: the release PR
assembles the section from the fragments (#112), and the monotonic guard
refuses anything that deletes a shipped heading.
- Follow the repo's conventions file and match the code you touch. Tests are
not optional: the issue's test plan is the floor, not the ceiling.
- **A write-capable job gets a repo-owned script, not a third-party action.**
Where the job's token can write (`packages: write`, `contents: write`,
`id-token: write`, deploy secrets), default to a script in the repo that a
test can drive; a third-party action there needs an established publisher
and a full-commit-SHA pin, and read-only jobs still SHA-pin. The full rule
and the red-flag profile a reviewer applies are in REVIEWER.md §What you
review against, item 2 (#216).
- **Scope discipline: the PR does the issue — whole, and nothing else.**
Adjacent problems go to a **discussion**, or a comment on the relevant
issue, where triage does its job. You do not mint issues — nobody but
triage does — and you do not fix drive-by findings in the same PR, because
a reviewer cannot converge on a widening target.
## The review round
(Read as `.ceremony/BUILDER.md` in a governed repo: repo-specific facts such
as the panel roster live in that repo's own CONTRIBUTING, and the shared
flow lives here.)
1. Mark ready-for-review; request **the whole panel**: the PR repo's
`panel[<your-login>]=` line if it defines one, else its `panel=` line,
minus the author in either case (#224) — never the roster of the repo the
issue is in. That repo's `.github/labels.conf` governs over its
CONTRIBUTING roster, being what the state machine reads; where the PR
repo names no roster, ask triage on the authorizing issue before marking
ready-for-review rather than guessing. You may request an off-panel
reviewer, saying that their verdict is advisory and does not become
required.
**A review request requires a green check at the head**, and that binds
you whether or not any engine enforces it: a red check is the author's
own signal, not the panel's work, so fix it and push, then request. The
one exception is a failure genuinely outside the PR — a runner outage, a
flaky dependency, a failure already present on the default branch — and
only where the request says so explicitly and names the evidence ("the
same job fails identically on `origin/main` at `<sha>`"). Silence about a
red check is what is prohibited; an argued exception shifts the burden to
the author.
*Green* is a ruled term (operator, 2026-07-27), read in two steps,
because a head carries more rollup entries than it has checks. **First
find the check's word at this head**: its newest entry by start time,
except that a `CANCELLED` entry is never the word while the same check
has a non-cancelled entry at that head. Date entries by start and not by
completion — a cancelled run outlives its replacement's start, so the
other reading picks the corpse. A check whose every entry at the head is
cancelled has not reported at all and stays not-green by the classes
below; that is a collapse, not a new class, and the gate partitions the
same way, dropping a cancelled entry only where its context keeps a
non-cancelled survivor (#139, #276).
**Then classify that entry from its `conclusion`, never its `status`**,
which can still disagree with it (#259). No conclusion at all is neither
class: a configured run still in progress is not green, and waiting on it
is compliance, not a stall. **Cancelled or stale** is not green — *stale*
means a superseded head's check, which a head-scoped rollup never shows,
so what survives there is same-head cancellation. **Skipped or neutral**
*is* green: those are deliberate "passed / not applicable" conclusions,
and reddening them would red every conditional job the fleet skips on
purpose. **No checks configured** is the third ruled case, not an argued
exception: nothing is configured, so nothing is waited for and the
request goes out at once, no evidence owed. That rules
nothing-configured, never nothing-answered-yet — a pending run has an
owner, CI — and the machine partitions alike, admitting the ask on
`SUCCESS` and on `NONE` (#236). The costs behind the line are asymmetric:
a false green spends a three-reviewer round, a false red one author
session. What the *machine* drops from the rollup before grading is
crew's to describe.
2. **Wait for every verdict, then answer the round whole** — one reply
covering every point and stating what changed and what was verified. That
reply is the written round record: the engine mirrors it under the PR
body's **Round log**, newest last, so the builder owes the reply and no
separate body edit, and a round answered without one is recorded as such
and never blocks handoff.
Then push the fixes and re-request **by head, not by verdict**. A push
makes every approval stale — an approval is of a specific tree, and the
handoff predicate counts only approvals at the current head — so **every
panelist is re-requested, the approvers included**; one left
un-re-requested can never approve the tree you shipped, and the PR sits
looking finished with nothing owed by anyone (#26, #39). Only where the
head did not move — the round answered with argument or evidence, nothing
pushed — do you re-request just the non-approvers, a standing approval
already covering this exact head (#94). **The re-request carries the same
green-check-at-head precondition as the first request**, argued exception
included: a fix push whose check comes up red is your next fix, not the
panel's. Prefer verification over argument — where a reviewer doubts
behavior, add the test that settles it.
3. Never dismiss a review, never merge, never mark your own work as passed.
A blocking point you disagree with is answered with evidence or escalated
in the PR; silence and force-forward are not options, and a panel
deadlock is one kind of human-owned decision (#50 D11).
**A fix round may ride a draft**, and the draft changes nothing about who
owes what. An engine may convert a PR back to draft when a round closes, so
that mid-round saves stop firing CI on a ready PR; ceremony implements no
such conversion and this passage specifies none, but whoever meets a
mid-round draft reads it as a draft always read — the draft phase is yours
and the panel cannot see it — while the round outranks the draft, so you
still owe it whole, the fixes and the reply and the flip
([LABELS.md](LABELS.md)'s `state:building` row, #205). **Ready-for-review is
the act that ends the round, and it is the builder's alone**: the flip
asserts that the round was answered whole, the one judgement about a round
its author cannot delegate, so an engine may draft a PR but only the builder
undrafts it. **Where a draft suppressed the checks, green is proven at the
flip and the request still follows it**: marking ready is what runs the
checks the draft held back, so the order is flip, let the head answer, then
request — step 1's precondition, not a second one. Waiting there is
compliance, not a stall, and `blocker:unrequested` does not fire while a
head's checks are pending or red, because the one blocker that demands an
act has to know when the act is permitted (#236).
## The ruling ask
Set `needs-ruling` whenever a decision belongs to a human: org policy,
published artifacts, secrets, prod, or any choice whose cost lands outside
the PR. A panel deadlock is one instance, not the definition. The builder is
the accountable flag-setter on a PR and consolidates the decision into one
comment rather than forwarding several reviewers' phrasings (#50 D11).
Keep at most these five lines above the fold and put all other analysis
inside the fold. The field labels are fixed because the ruling machinery
checks for them (#50 D12):
```text
🧭 needs-ruling — <the decision, one line>
Options: A — <one clause> B — <one clause>
Recommend: A, because <one clause>.
Blocked: <what stops; what continues meanwhile>
Default: <A at 2026-07-23T21:00Z if no ruling> | none — hard block
<details><summary>Analysis</summary>…everything else…</details>
```
The options must be exhaustive and mutually exclusive; more than three means
the question is not ready. `Recommend:` is mandatory — omitting it hands the
whole problem to the human. `Blocked:` names both what stops and what
continues. Write a timed `Default:` only when you are affirmatively confident
the decision is reversible inside the PR before merge. Unsure is not a tie:
it is a hard block. Published artifacts, secrets, prod, and org policy are
hard blocks by construction (#50 D12D13).
The ladder is anchored to the current episode's `needs-ruling` **`labeled`
event**, not its `Default:` deadline or the last activity (#50 D13D14):
- **012h:** proceed when a still-clear, reversible default expires, and say
out loud that you did. A hard block waits.
- **at 12h:** do not fire a stale default. Re-read it against what has landed
and ask whether it still holds and whether reasonable doubt remains. If
doubt has appeared, make it a hard block.
- **at 24h:** proceed regardless, **as a PR**. Pick an option and state in the
PR body which way you went and what doubt remains. Nothing merges by this;
the human still gates the merge.
- **past 24h:** hand the choice to triage. Triage picks the option, records it
as a decision, and remains accountable; the operator can overturn it at
merge.
A re-flag starts a fresh ladder. The ladder applies whatever `Default:` says,
including a hard block, and an active back-and-forth still climbs it. This is
different from the 7-day nudge, which resets on real activity. The machine
observes both clocks but never sets, clears, or decides `needs-ruling`.
The label stays until agreement is *reached*, not until the maintainer
replies. The setter records the ruling, removes the label, and returns the
item to its flow in the same comment ([LABELS.md](LABELS.md)).
## Handoff
When the round passes — every panel verdict approves the **current head**,
and no `blocker:*` stands (conflicts rebased, CI green, drill recorded if
2026-07-28 17:57:31 +00:00
this is a release PR) — the engine performs these mechanical steps on the
builder's behalf, in order:
1. request the human's review;
2026-07-28 17:57:31 +00:00
2. set `state:needs-human`;
3. post the engine-rendered handoff comment: approvals at the current head,
the head SHA, and a pointer to the PR body's **Round log**.
The builder composes no new summary at handoff: the authored record already
lives in the Round log, mirrored from each whole-round reply. The label write
is optimistic — the reconciler validates it and takes it back if the PR is
not actually mergeable-right-now. Then stop: the PR is the human's, and the
claim is parked as shape 4 (Picking, above), that handoff comment being its
declaration and your build slot free. Address what comes back
(`state:addressing`) and re-hand-off the same way.